Hi Richard,
As you mentioned, they are not visible in 3D, so as a matter of fact, the ducts are important for the BOM (bill of materials) in the Estimator → therefore the simple solution is considering the duct as a rectangular prism
Try this → say your duct line is 20" x 20" and you need a vertical line to connect 2 horizontal lines, separated by a vertical distance= 120" → HVAC tab → Air duct tool (first icon from the left) → Trace a duct with Length= 20" → Right pane → Tool Options → set the Width= 20" → set the Depth= 120" → you have a vertical duct with 20"x20" and height= 120"
See attached
Note: don’t forget to press Enter in your keyboard after each change in the right pane, so the change takes effect
Patricia